Production: how we make and install sign supports

  • Welding the base
  • Hot-dip galvanising
  • Concrete foundation
  • Assembly on the ground
  • Crane lift

We make sign supports in a full cycle: steelwork, protective coating, foundation, assembly and installation. Here is how the work goes.

How we make and install supports

  1. Welding the base
    1

    Welding the base

    The post is welded to the base plate; triangular gussets add stiffness and offset the lever of a long cantilever.

  2. Hot-dip galvanising
    2

    Hot-dip galvanising

    The structure is dipped into a zinc bath: the coating is even and the support needs no yearly repainting.

  3. Concrete foundation
    3

    Concrete foundation

    The rebar cage and anchors are set with a jig so the plate holes match the anchors exactly.

  4. Assembly on the ground
    4

    Assembly on the ground

    The cantilever and the sign are assembled at ground level — safer and more precise than working at height.

  5. Crane lift
    5

    Crane lift

    The finished support is lifted as one unit and plumbed with the levelling nuts. Traffic closure is kept to a minimum.